Case Studies
1st Tier Automotive Supplier
The Brief
Our client required 5000 chrome plated plastic parts for an exterior vehicle application.
The Solution
An Aluminium Rapid Tool was manufactured using high speed CNC milling.The production parts were then injection moulded in PC ABS, verified and chrome plated.
Performance
The tooling was completed in 7 working days and first off parts arrived at the customer 2 days later.
The Benefits
Production parts to market within 10 days from order. Considerable saving over conventional High Volume tooling methods.